One stop service for steel industry

The Electric Arc Furnace – Part 3 (Operation)

Table of Contents

[vc_row][vc_column][ult_buttons btn_title=”The Electric Arc Furnace – Part 3 (Operation)” btn_align=”ubtn-center” btn_size=”ubtn-large” btn_title_color=”#ffffff” btn_bg_color=”#f25410″ icon_size=”32″ btn_icon_pos=”ubtn-sep-icon-at-left” btn_font_style=”font-weight:bold;” btn_font_size=”desktop:20px;”][vc_column_text css=”.vc_custom_1589361934862{margin-top: 30px !important;}”]ELECTRIC ARC FURNACE STEELMAKING[/vc_column_text][/vc_column][vc_column][vc_column_text]

This is the third of the series of EAF for steelmaking. It focuses on the operation part of EAF production.

[/vc_column_text][/vc_column][/vc_row][vc_row][vc_column][vc_text_separator title=”Operation”][/vc_column][/vc_row][vc_row][vc_column][vc_column_text]A mid-sized modern steelmaking furnace would have a transformer rated about 60,000,000 volt-amperes (60 MVA), with a secondary voltage between 400 and 900 volts and a secondary current in excess of 44,000 amperes. In a modern shop such a furnace would be expected to produce a quantity of 80 metric tonnes of liquid steel in approximately 50 minutes from charging with cold scrap to tapping the furnace.- The Electric Arc Furnace[/vc_column_text][/vc_column][/vc_row][vc_row][vc_column][vc_column_text]In comparison, basic oxygen furnaces can have a capacity of 150–300 tonnes per batch, or “heat”, and can produce a heat in 30–40 minutes. Enormous variations exist in furnace design details and operation, depending on the end product and local conditions, as well as ongoing research to improve furnace efficiency. The largest scrap-only furnace (in terms of tapping weight and transformer rating) is a DC furnace operated by Tokyo Steel in Japan, with a tap weight of 420 metric tonnes and fed by eight 32MVA transformers for 256MVA total power.[/vc_column_text][/vc_column][/vc_row][vc_row][vc_column][vc_column_text]To produce a ton of steel in an electric arc furnace requires approximately 400 kilowatt-hours per short ton or about 440 kWh per metric tonne; the theoretical minimum amount of energy required to melt a tonne of scrap steel is 300 kWh (melting point 1520 °C/2768 °F).[/vc_column_text][/vc_column][/vc_row][vc_row][vc_column][vc_column_text]Therefore, a 300-tonne, 300 MVA EAF will require approximately 132 MWh of energy to melt the steel, and a “power-on time” (the time that steel is being melted with an arc) of approximately 37 minutes. Electric arc steelmaking is only economical where there is plentiful electricity, with a well-developed electrical grid.[/vc_column_text][/vc_column][/vc_row][vc_row][vc_column][vc_column_text]In many locations, mills operate during off-peak hours when utilities have surplus power generating capacity and the price of electricity is less.[/vc_column_text][/vc_column][/vc_row][vc_row][vc_column][vc_column_text]The scrap is loaded into large buckets called baskets, with “clamshell” doors for a base. Care is taken to layer the scrap in the basket to ensure good furnace operation; heavy melt is placed on top of a light layer of protective shred, on top of which is placed more shred.[/vc_column_text][/vc_column][/vc_row][vc_row][vc_column][vc_column_text]These layers should be present in the furnace after charging. After loading, the basket may pass to a scrap pre-heater, which uses hot furnace off-gases to heat the scrap and recover energy, increasing plant efficiency.[/vc_column_text][/vc_column][/vc_row][vc_row][vc_column][vc_column_text]The scrap basket is then taken to the melt shop, the roof is swung off the furnace, and the furnace is charged with scrap from the basket. Charging is one of the more dangerous operations for the EAF operators.[/vc_column_text][/vc_column][/vc_row][vc_row][vc_column][vc_column_text]A lot of potential energy is released by the tonnes of falling metal; any liquid metal in the furnace is often displaced upwards and outwards by the solid scrap, and the grease and dust on the scrap is ignited if the furnace is hot, resulting in a fireball erupting.[/vc_column_text][/vc_column][/vc_row][vc_row][vc_column][vc_column_text]In some twin-shell furnaces, the scrap is charged into the second shell while the first is being melted down, and pre-heated with off-gas from the active shell. Other operations are continuous charging—pre-heating scrap on a conveyor belt, which then discharges the scrap into the furnace proper, or charging the scrap from a shaft set above the furnace, with off-gases directed through the shaft. Other furnaces can be charged with hot (molten) metal from other operations.[/vc_column_text][/vc_column][/vc_row][vc_row][vc_column][vc_column_text]After charging, the roof is swung back over the furnace and meltdown commences. The electrodes are lowered onto the scrap, an arc is struck and the electrodes are then set to bore into the layer of shred at the top of the furnace.[/vc_column_text][/vc_column][/vc_row][vc_row][vc_column][vc_column_text]Lower voltages are selected for this first part of the operation to protect the roof and walls from excessive heat and damage from the arcs. Once the electrodes have reached the heavy melt at the base of the furnace and the arcs are shielded by the scrap, the voltage can be increased and the electrodes raised slightly, lengthening the arcs and increasing power to the melt.[/vc_column_text][/vc_column][/vc_row][vc_row][vc_column][vc_column_text]This enables a molten pool to form more rapidly, reducing tap-to-tap times. Oxygen is blown into the scrap, combusting or cutting the steel, and extra chemical heat is provided by wall-mounted oxygen-fuel burners. Both processes accelerate scrap meltdown. Supersonic nozzles enable oxygen jets to penetrate foaming slag and reach the liquid bath.[/vc_column_text][/vc_column][/vc_row][vc_row][vc_column][vc_column_text]Once the scrap has completely melted down and a flat bath is reached, another bucket of scrap can be charged into the furnace and melted down, although EAF development is moving towards single-charge designs.[/vc_column_text][/vc_column][/vc_row][vc_row][vc_column][vc_column_text]After the second charge is completely melted, refining operations take place to check and correct the steel chemistry and superheat the melt above its freezing temperature in preparation for tapping. More slag formers are introduced and more oxygen is blown into the bath, burning out impurities such as

Removal of carbon takes place after these elements have burnt out first, as they have a greater affinity for oxygen. Metals that have a poorer affinity for oxygen than iron, such as nickel and copper, cannot be removed through oxidation and must be controlled through scrap chemistry alone, such as introducing the direct reduced iron and pig iron mentioned earlier.

 

A foaming slag is maintained throughout, and often overflows the furnace to pour out of the slag door into the slag pit. Temperature sampling and chemical sampling take place via automatic lances. Oxygen and carbon can be automatically measured via special probes that dip into the steel, but for all other elements, a “chill” sample—a small, solidified sample of the steel—is analysed on an arc-emission spectrometer.

 

Once the temperature and chemistry are correct, the steel is tapped out into a preheated ladle through tilting the furnace. For plain-carbon steel furnaces, as soon as slag is detected during tapping the furnace is rapidly tilted back towards the deslagging side, minimising slag carryover into the ladle.

 

For some special steel grades, including stainless steel, the slag is poured into the ladle as well, to be treated at the ladle furnace to recover valuable alloying elements. During tapping some alloy additions are introduced into the metal stream, and more lime is added on top of the ladle to begin building a new slag layer.

 

Often, a few tonnes of liquid steel and slag is left in the furnace in order to form a “hot heel”, which helps preheat the next charge of scrap and accelerate its meltdown. During and after tapping, the furnace is “turned around”.

 

The slag door is cleaned of solidified slag, the visible refractories are inspected and water-cooled components checked for leaks, and electrodes are inspected for damage or lengthened through the addition of new segments; the taphole is filled with sand at the completion of tapping.

 

For a 90-tonne, medium-power furnace, the whole process will usually take about 60–70 minutes from the tapping of one heat to the tapping of the next (the tap-to-tap time).

 

The furnace is completely emptied of steel and slag on a regular basis so that an inspection of the refractories can be made and larger repairs made if necessary. As the refractories are often made from calcined carbonates, they are extremely susceptible to hydration from water, so any suspected leaks from water-cooled components are treated extremely seriously, beyond the immediate concern of potential steam explosions.

 

Excessive refractory wear can lead to breakouts, where the liquid metal and slag penetrate the refractory and furnace shell and escape into the surrounding areas.- The Electric Arc Furnace[/vc_column_text][/vc_column][/vc_row][vc_row btn_title=”Improve the ladle lining life” btn_link=”” btn_align=”ubtn-center” btn_size=”ubtn-large” btn_width=”” btn_height=”” btn_padding_left=”” btn_padding_top=”” btn_title_color=”#ffffff” btn_bg_color=”#6b96bf” ult_btn_custom_onclick=”” btn_hover=”ubtn-no-hover-bg” btn_anim_effect=”none” btn_bg_color_hover=”” btn_title_color_hover=”” button_bg_img=”” btn_icon_pos=”ubtn-sep-icon-at-left” btn_border_style=”” btn_color_border=”” btn_color_border_hover=”” btn_border_size=”1″ btn_radius=”3″ btn_shadow=”” btn_shadow_color=”” btn_shadow_color_hover=”” btn_shadow_size=”5″ btn_shadow_click=”” enable_tooltip=”” tooltip_text=”” tooltip_pos=”left” btn_font_style=”font-weight:bold;” btn_font_size=”desktop:20px;” rel_attr=”” ult_btn_custom_onclick_code=”” css_adv_btn=”” btn_font_family=”” btn_line_height=””][vc_column][ult_buttons btn_title=”LMM GROUP ONE STOP SERVICE FOR STEEL INDUSTRY” btn_align=”ubtn-center” btn_size=”ubtn-small” btn_title_color=”#ffffff” btn_bg_color=”#ce6616″ icon_size=”32″ btn_icon_pos=”ubtn-sep-icon-at-left” btn_font_style=”font-weight:bold;” btn_font_size=”desktop:20px;”][/vc_column][/vc_row][vc_row][vc_column width=”1/2″][ult_buttons btn_title=”Get more information on the steel industry” btn_link=”url:https%3A%2F%2Fwww.lmmgroupcn.com%2Fsteel-industry-technology%2F||target:%20_blank|” btn_align=”ubtn-center” btn_size=”ubtn-small” btn_title_color=”#ffffff” btn_bg_color=”#ed8b0b” icon_size=”32″ btn_icon_pos=”ubtn-sep-icon-at-left” btn_font_style=”font-weight:bold;” btn_font_size=”desktop:20px;”][/vc_column][vc_column width=”1/2″][ult_buttons btn_title=”This article is reproduced, the original link” btn_link=”url:https%3A%2F%2Fgraphite-network.com%2F2019%2F08%2F21%2Fthe-electric-arc-furnace-part-3-operation%2F||target:%20_blank|” btn_align=”ubtn-center” btn_size=”ubtn-small” btn_title_color=”#ffffff” btn_bg_color=”#ed8b0b” icon_size=”32″ btn_icon_pos=”ubtn-sep-icon-at-left” btn_font_style=”font-weight:bold;” btn_font_size=”desktop:20px;”][/vc_column][/vc_row]

Facebook
Twitter
LinkedIn
Reddit

As professional one-stop solution provider, LIAONING MINERAL & METALLURGY GROUP CO., LTD(LMM GROUP) Established in 2007, and focus on engineering research & design, production & delivery, technology transfer, installation & commissioning, construction & building, operation & management for iron, steel & metallurgical industries globally. 

Our product  have been supplied to world’s top steel manufacturer Arcelormittal, TATA Steel, EZZ steel etc. We do OEM for Concast and Danieli for a long time.

LMM Main product series

Core technology products:

  • magnesia carbon brick
  • slide gate plate
  • graphite electrode

Core technology products:

  • Hss roller
  • cast steel rolls
  • tungten carbide ring roller

Core technology products:

  • copper mould tube
  • copper mould plate
  • assembly & cooling jackts

Need For Some Help ?

Professional engineers provide solutions and technical drawings

phone

86(411) 84174804

mail

lmme-business@lmmgroup.com.cn

Special product design, please send specific data and drawings to our mailbox or form.

As professional one-stop solution provider, LIAONING MINERAL & METALLURGY GROUP CO., LTD(LMM GROUP) Established in 2007, and focus on engineering research & design, production & delivery, technology transfer, installation & commissioning, construction & building, operation & management for iron, steel & metallurgical industries globally. 

Our product  have been supplied to world’s top steel manufacturer Arcelormittal, TATA Steel, EZZ steel etc. We do OEM for Concast and Danieli for a long time.

LMM GROUP Certification

LMM GROUP Service

Get A Free Consultation
And Estimate